Construction of platform shelters, an extension to Maison Alfort station and a large urban canopy on the Alfortville side.
The canopies are all based on the same design: standing seam zinc roofing on wooden battens, with or without thermal insulation (VMZ structural roofing system), T-shaped metal rafter framework.
Creation of windows in the walls of the historic station, renovation of the floors.
Client: Gares et Connexions
Project manager: AREP - MaP3 (Structure)
Contractors: CBI (Structural works) - Vilquin (Roof framing) - Soluglob (Facades)
Completion: 2018
Technical data: Project area: 2,000 m²
Localisation et Année de livraison :
France
- Alfortville
- 2017
Les maitres d’oeuvres :
AREP - MaP3 (Structural Engineering Consultancy)
Galerie